Reggie’s quick take
Someone asked whether German-made UN 31A IBCs and UN 1A1 steel drums can be used in the U.S. when their design tests were done more than 12 months ago with no later testing. Under § 173.24(d), foreign-made UN packagings need no PHMSA Associate Administrator approval if they fully meet the UN Recommendations and Part 173, Subpart B, can pass the Part 178 tests, and Germany gives reciprocal treatment to U.S.-made UN packagings. In that case, a retest interval longer than 12 months is allowed when Germany's competent authority authorizes it.
Written by AI (Claude) on Oct 22, 2026. Robots make mistakes and leave things out, so the letter below is what counts. Not legal advice.
This responds to your request for clarification of the Hazardous Materials Regulations (HMR; 49 CFR Parts 171-180) regarding the periodic design requalification testing and authorization for use in the United States (U.S.) of certain UN specification packagings. Specifically, you ask whether new single packagings, UN 31A rigid intermediate bulk containers (IBCs) and UN 1A1 non-removable head steel drums, that are manufactured and marked in Germany, are authorized for use in the United States if the original design qualification tests were conducted more than 12 months ago with no subsequent testing. You also ask whether approval must be obtained from the Associate Administrator of Hazardous Materials Safety (Associate Administrator), Pipeline and Hazardous Materials Safety Administration (PHMSA), U.S. Department of Transportation (DOT), if the German-manufactured packages do not conform to the HMR's frequency requirements for periodic design requalification testing and also whether the Associate Administrator's approval must be obtained if the German manufacture complies with the HMR's 12-month frequency testing requirement with the approval of the German competent authority. You reference §§ 173.24, 178.601 and 178.801 in your letter.
With respect to the frequency intervals for periodic design requalification testing, §§ 178.601(e) and 178.801(e) apply to U.S. manufactured packagings. Section 173.24(d) authorizes the import and use of foreign manufactured specification and UN standard packagings in the U.S. provided: (1) the packagings fully conform to applicable provisions in the UN Recommendations and the requirements of Part 173, Subpart B, including reuse provisions; (2) the packagings are capable of passing the prescribed tests in Part 178 of this subchapter applicable to the standard; and (3) the competent authority of the country of manufacture provides reciprocal treatment for UN standard packagings manufactured in the United States. When these provisions are met, approval from DOT/PHMSA's Associate Administrator is not required for German-manufactured UN 31A IBCs and UN 1A1 drums with a periodic design requalification testing frequency interval that is longer than the HMR's 12-month frequency testing interval when authorized by Germany's competent authority. Further, Associate Administrator approval is not required if the German manufacturer complies with the HMR's 12-month frequency testing requirement with the approval of the German competent authority.
A letter of interpretation applies the regulations to the facts the requester described. It isn’t a regulation and isn’t legal advice. The agency’s copy.