49 CFR § 190.401 Pipeline Safety Enforcement and Regulatory Procedures

§ 190.401 Scope.

Current through Sep 25, 2026 · Read all of Part 190

⚠ 1 pending change to Part 190

If PHMSA conducts a facility design and/or construction safety review or inspection in connection with a proposal to construct, expand, or operate a gas, hazardous liquid or carbon dioxide pipeline facility, or a liquefied natural gas facility that meets the applicability requirements in § 190.403, PHMSA may require the applicant proposing the project to pay the costs incurred by PHMSA relating to such review, including the cost of design and construction safety reviews or inspections.

← § 190.343 Information made available to the public and request for protection of confidential commercial information.§ 190.403 Applicability. →