48 CFR § 511.503 Describing Agency Needs

511.503 Contract clauses.

Current through · Read all of Part 511

(a) Insert the clause at 552.211-12, Liquidated Damages-Construction, in solicitations and contracts for construction, other than cost-plus-fixed-fee, when the contracting officer determines that liquidated damages are appropriate (see FAR 11.501(a)).

(b) Insert the clause at 552.211-13, Time Extensions, in solicitations and contracts for construction that includes the clause at 552.211-12.

[86 FR 55518, Oct. 6, 2021]