40 CFR § 280.61 Technical Standards and Corrective Action Requirements for Owners and Operators of Underground Storage Tanks (UST)

§ 280.61 Initial response.

Current through Aug 22, 2025 · Read all of Part 280

Upon confirmation of a release in accordance with § 280.52 or after a release from the UST system is identified in any other manner, owners and operators must perform the following initial response actions within 24 hours of a release or within another reasonable period of time determined by the implementing agency:

(a) Report the release to the implementing agency (e.g., by telephone or electronic mail);

(b) Take immediate action to prevent any further release of the regulated substance into the environment; and

(c) Identify and mitigate fire, explosion, and vapor hazards.