32 CFR § 37.905 Technology Investment Agreements

§ 37.905 Must I make receipt of the final performance report a condition for final payment?

Current through Mar 4, 2026 · Read all of Part 37

If a final report is required, your TIA should make receipt of the report a condition for final payment. If the payments are based on payable milestones, the submission and acceptance of the final report by the Government representative will be incorporated as an event that is a prerequisite for one of the payable milestones.

← § 37.900 May I tell a participant that information in financial and programmatic reports will not be publicly disclosed?§ 37.910 How long must I require participants to keep records related to the TIA? →