30 CFR § 585.652 Renewable Energy on the Outer Continental Shelf

§ 585.652 How long do I have to conduct activities under an approved GAP?

Current through Jul 27, 2026 · Read all of Part 585

After BOEM approves your GAP, you have:

(a) For a limited lease, the time period established under § 585.236(a)(2), unless we renew the operations period under §§ 585.425 through 585.429.

(b) For a ROW grant or RUE grant, the time provided in the terms of the grant.