30 CFR § 285.910 Renewable Energy and Alternate Uses of Existing Facilities on the Outer Continental Shelf

§ 285.910 What must I do when I remove my facility?

Current through Jul 27, 2026 · Read all of Part 285

(a) You must remove all facilities to a depth of 15 feet below the mudline, unless otherwise authorized by BSEE.

(b) Within 60 days after you remove a facility, you must verify to BSEE that you have cleared the site.