10 CFR § 76.55 Certification of Gaseous Diffusion Plants

§ 76.55 Timely renewal.

Current through Oct 5, 2026 · Read all of Part 76

⚠ 1 pending change to Part 76

In any case in which the Corporation has timely filed a sufficient application for a certificate of compliance, the existing certificate of compliance or approved compliance plan does not expire until the application for a certificate of compliance has been finally determined by the NRC. For purposes of this rule, a sufficient application is one that addresses all elements of § 76.36.

[62 FR 6670, Feb. 12, 1997]