§ 53.770 Incapacitation because of disability or illness.

Current through Oct 5, 2026 · Read all of Part 53

⚠ 7 pending changes to Part 53

If, during the term of the operator or senior operator license, the licensee develops a permanent physical or mental condition that causes the licensee to fail to demonstrate compliance with the requirements of § 53.775(b)(1)(i), the facility licensee must notify the Commission within 30 days of learning of the diagnosis. For conditions for which a conditional license (as described in § 53.775(b)) is requested, the facility licensee must provide medical certification on NRC Form 396 to the Commission (as described in § 53.765(b)).