10 CFR § 52.173 Licenses, Certifications, and Approvals for Nuclear Power Plants

§ 52.173 Duration of manufacturing license.

Current through Oct 5, 2026 · Read all of Part 52

⚠ 10 pending changes to Part 52

A manufacturing license issued under this subpart may be valid for not less than 5, nor more than 15 years from the date of issuance. A holder of a manufacturing license may not initiate the manufacture of a reactor less than 3 years before the expiration of the license even though a timely application for renewal has been docketed with the NRC. Upon expiration of the manufacturing license, the manufacture of any uncompleted reactors must cease unless a timely application for renewal has been docketed with the NRC.

← § 52.171 Finality of manufacturing licenses; information requests.§ 52.175 Transfer of manufacturing license. →