10 CFR § 52.153 Licenses, Certifications, and Approvals for Nuclear Power Plants

§ 52.153 Relationship to other subparts.

Current through Oct 5, 2026 · Read all of Part 52

⚠ 10 pending changes to Part 52

(a) A nuclear power reactor manufactured under a manufacturing license issued under this subpart may only be transported to and installed at a site for which either a construction permit under part 50 of this chapter or a combined license under subpart C of this part has been issued.

(b) Subpart B of this part governs the certification by rulemaking of the design of standard nuclear power facilities. Subpart E of this part governs the NRC staff review and approval of standard designs for a nuclear power facility. A manufacturing license applicant may reference a standard design certification or a standard design approval in its application. These subparts may also be used independently of the provisions in this subpart.

← § 52.151 Scope of subpart.§ 52.155 Filing of applications. →